Cost Breakup for a Pipeline Project

Sr.No.

Item Description

Percentage of Capital Cost

Liquid Lines

Gas Lines

1

Survey, ROW and Compensation

2%

1%

2

Line Pipe Steel Cost

33%

45%

3

Main Line Materials

2%

3%

4

Coating of Pipes

11%

6%

5

Main Line Construction

33%

25%

6

Cathodic Protection

1%

1%

7

Telecommunications, SCADA and RCPs

5%

2%

8

Pump / Compressor Stations

5%

12%

9

Delivery Terminal Facilities

2%

1%

10

Project Management

5%

4%

 

SubTotal

100%

100%