Have you watched this viral time-lapse
webcam footage, which is all over Youtube,
Facebook, Twitter of a Dutch tunnel
construction that took up only the weekend of the 20th to the 22nd of May?
This footage shows that efficient
planning of construction methods can speed up construction. Structural
engineering is not just about understanding structural theories, but also
determining the optimal construction methods that will benefit cost, time, and
productivity.
The construction process of the Dutch tunnel
had three activities:
1. Demolition of existing overpass
2. Installation of prefabricated tunnel
3. Rebuilding the overpass to be wider
1. Demolition of existing overpass
2. Traffic was
initially diverted. Then, four cranes were used to
demolish portions of the existing overpass and soil.
3. Installation of prefabricated tunnel
4. The prefabricated 70m long fauna tunnel
with noise dampening asphalt was then slowly aligned into
place under the highway overpass, while demolition was just at its last stages.
After the tunnel was installed in its
position, cranes were then used to fill the gaps between the tunnel and the
paving with backfill.
5. Rebuilding the overpass to be wider
6. The tunnel installation also resulted a
new three-lane highway and one shoulder.
Constructing through the Storm Source:
http://www.express.co.uk/
The fast construction demonstrates that
effective planning and management of construction methods and techniques can
make projects more cost-effective and less time consuming. Here were some
construction techniques that were used:
1. Temporary diversion of traffic
2. Traffic was
temporarily diverted to an alternative route so that the
construction operation will only cause minimal disruption to the traffic.
3. Modular or prefabricated construction
4. Preassembled fabricated tunnel was used, so that the tunnel can be made of high quality,
with good tolerances, and in a more controlled environment. Less waste was also accumulated. Since the tunnel was prefabricated
elsewhere and not placed insitu on site,
more space was created due to the delivery
of the tunnel assembly. Installation of the tunnel was rapid due to the lack of
site constraints.
5. Demolition of the overpass was a
parallel operation to the tunnel installation.
6. Time was saved when
the overpass was demolished from the edge to the middle of the overpass. When
the edge of the overpass was demolished and
demolition was continuing at the middle of the overpass, the tunnel can be
installed simultaneously with the demolition works at the middle of the
overpass.
7. Use of porous asphalt during the storm
8. Porous asphalt was
used so that workers can pave and strip in the storm. Stormwater can move through the large voids in the
porous asphalt, which makes permeable paving possible. After installation of
the paving, porous asphalt can also decrease water runoff and conserve water
when water infiltrates the asphalt, moves into the stone bed, and into the
soil. Contaminants in the stormwater are removed when the water passes through the asphalt
and stone bed. The decrease of water on the pavement also makes driving safer.
This shows us that man can work at an amazing
pace. With the ever changing technologies
and innovative strategies, we have the power to complete projects in a cost
effective and timely manner and in any conditions and environment. Therefore,
during the design process, not only should we consider the structural integrity
of the structure, we also need to consider the constructability of critical
structures, the coordination of trades and machinery, and the efficient use or
allocation of resources.