Electrical System Of A Thermal Plant - Abc Of Thermal Power Plant.

 

Beside that in Turbine package there are other auxiliaries both static and rotary such as different coolers , CEP ( condensate extraction pump ) , vacuum pumps , CPU ( condensate polishing unit) etc. Except CEP erection of other auxiliaries need not require any special strategy. For CEP erection foundation checking and canister erection is slightly crtical. CEP is a vertical pump therefore canister is to be erected before erection of CEP. It is sometimes noticed that CEP foundation is full of water at bottom most area and prevent  canister erection . It is recommended to repair the foundation so that leakage can be stopped or draining the pit before erection.

 

It was decided that next topics will be steam blowing as we have covered all the major equipment . However i received mails from young engineers to cover electrical system erection and commissioning . I am an electrical engineer but did not work with the system. Therefore what i have seen at site is written down. Value addition is to be done by individual. 
Earthing system is the mother of electrical system. You can not run an electrical machine without earthing.

The  earthing system consists of  following. Earthing is the basic requirement of any  Good electrical system. This is essential to protect human lives and also help us to detect fault in the system . Good earthing  provides smooth electrical operation  and avoid spurious tripping.

 

i.              Earth Pit

ii.             Subsidiary conductors

 

iii.            GI Flats

 

1.            EARTH PIT :   Each earth pit must be made as per their design normally that will be either pipe or rod electrode type earth pits.  In pipe electrode earth pit the depth will be 3.5 Mtr . Where as in rod electrode the depth will be 3 Mtr only.  In pipe electrode,  the earth pit must be made with different layers of  sand, coal, salt  and gravel  whereas in rod electrode, the rod will be inserted into the earth soil. BTG area earth mat was laid after  doing the PCC of the area. Risers were raised along the column foundation from two sides. Rods are welded at least 250 mm overlap so that firm contact is made.  Special earth pits are made for electronic panels and skids which are separated from electrical earthing. 

 

2.            SUBSIDIARY CONDUCTORS :  The conductors connects between earth pit and various equipments are subsidiary conductors.  They are connected with main earth mat  which is  600 mm depth by means of   raiser  and will be connected to each earth pit through test links.  The other end of the earth pit will be connected to the equipment.

 

3.            GI FLATS :  All the test links and equipment connections of the switch yard are  done with GI flats of 75 x 12 mm .  Inside the control building, the earthing connection is provided by 50x6 mm GI flats. 

 

Testing

-             To test the individual earth pits of 400 KV switch yard

-              To test the continuity of the earth mat

-             To measure the resistance of  total earth mat.

 

Testing Equipment

-          Earth  Megger calibrated.

 -     Calibrated digital multimeter.

 

State  of the plant

 

Erection of 400 KV Switch yard earthing network completed.

 

Test links and connections to various equipments disconnected for test.

 

Clearance from erection department for carrying out various tests obtained.