PRE – ENERGISING CHECKS & TESTS
-Inspect any physical damage in the busbar, insulation, panel doors, power & sliding contacts etc. and to be rectified if found. Special attention to be given on porcelain insulators holding the live line
-Making the panel inside dust free & free from foreign materials
-Checking the tightness alignment & clearance of bus bars ,smoothness in racking in & racking
out of modules, proper making of limit switch contacts(test and service), tightness of input power cables and outgoing power & control internal wirings.
-Inspect all relays and make sure that any blocking used for shipping purpose is removed and the
armature moves freely.
-Check all doors for proper mounting with respect to the switch handle.
-Check door interlock mechanism and connection.
-Test the pts,cts & relays involved. keep the recommended settings for the relays like over
current, under voltage & overload protections, calibrate the meters (ammeters, voltmeters, power
meters & energy meters etc) and keep proper records for future reference.
- Test the insulation of boards with 5000 v dc megger & the value should be as per the relevant
is specification (more than 50 mega ohms).
-Check closing & tripping interlocks ,overload relay setting in the panel.
-Measure busbar resistance , vcbs contact resistance (should be less than 50 milli ohms), closing
& tripping time if test report is not available at site.
-Check the protection circuit wiring connection by conducting primary injection current.
-Carry out high pot test for 75% of voltage mentioned in the test report for ht buses,100 % for ht
incoming power cables and find out the leakage current.
-Check the input power cable terminations from transformer secondary
-Ensure the phase sequence of incoming pt wirings and circuit closing of cts are proper before
charging the panel.
-Check closing & tripping mechanism operates smoothly both manually and electrically.
-Space heaters & thermostat shall be in good condition Space heaters to be ON a day before charging.
-Ensure all covers are provided and no conducting part is earthed. All the gland holes are covered
and temporarily sealed to minimize the short circuit of live terminal through rodents.
CHARGING PROCEDURE:
-Ensure tie breaker in associated station switchgear is in withdrawn position.
-Ensure all feeder breakers of unit Swtichgear are in withdrawn position.
-Check and record the final IR of supply cables for the DC control bus and the AC heater supplies :
-Energise both the supply cables for DC control bus and AC heater supplies.
-Put the tie breaker in Test position.
-Put all control fuses for the Tie breaker in position and switch on its control supply.
-Select LOCAL/REMOTE selector switch to local and close and trip the tie breaker once check its operation.
-Check tie isolator. Interlock in closing circuit of tie breaker.
-Check that tripping relays for Tie breaker and main incomer breaker are not operated and are reset.
-Select Tie breaker Local / Remote switch to REMOTE.
-Give closing impulse to Tie breaker from UCB and check that the breaker closes.
-Short Terminals (tripping contact of E/F and O/C Relay) and check that tripping relay energises and tie breaker trips.
-Switch off the control supply and reset the tripping relay and remove the shorts as detailed earlier.
-Put the incomer breaker in Test position.
-Put control fuses of Incomer breaker in position and switch on control supply.
-Select Local/Remote switch of Incomer breaker to local and close and trip the incomer breaker once to check its operation.
-Short the terminals in Incomer breaker cubicle to bypass the “Generator Breaker closed permissive”.
-Select Incomer breaker Local/Remote switch to Remote.
-Give closing command by control switch in UCB and check that the breaker closes.
-Switch on the control supply to tie breaker.
-Short terminals in incomer breaker and check that :
a. Incomer breaker trips
b. Tie breaker closes automatically
-Reset all alarms and relays and remove shorts.
-Give trip command to incomer breaker control switch in UCB to bring switch position corresponding to breaker position.
-Put check/manual switch for incomer breaker in UCB in MANUAL position.
-Give closing command to incomer breaker and check that :
a. Incomer breaker closes.
b. Tie breaker trips automatically.
-Reset all alarms and relays.
-Give trip command to tie breaker control switch in UCB to bring switch position corresponding to
breaker position.
-With incomer breaker ON and check/manual switch in manual position, give closing command to the tie breaker and check that :
a. Tie breaker closes;
b. Incomer breaker trips.
-Reset all alarms and relays.
-Trip the Tie breaker.
-Switch off the control supplies to both incomer and tie breakers.
-Remove all test connections and check that any disconnections made for the purposes of testing have been correctly reinstated in tie and incomer panels.
-Keep incomer breaker in withdrawn position (It will remain in withdrawn position till unit auxiliary
transformers are commissioned).
-Check ‘danger/warning notices’ are fixed at relevant points to ensure safety.
-Ensure effective communications between UCB and switch board room are established.
-Check and record the final IR value of the following equipments :
a Isolator/Tie breaker of associated station switchgear.
b.Tie breaker of Unit switchgear
c. Unit switchgear bus bar
d.Tie bus duct/cable megger used ___________ KV
-Ensure VT is in service position with all its fuses put on.
-Check all the relay settings in TIE breaker panel are as per their protection schedule.
ENERGIZING PROCEDURE
-Put the Tie breaker of associated station switchgear in service position and close the tie breaker to charge the Tie cable.
-Observe the cable for any abnormality.
-Put the tie breaker in service position.
-Switch on the control supply to the tie breaker.
-Inform all concerned parties about the intention of charging the unit switch board.
-Put local/remote switch of tie breaker in REMOTE position.
-Give closing command from the UCB to tie breaker to charge the unit switch board.
-Check and record the unit bus bar voltage for all the three phases.
-Observe the unit switch board for any abnormality.
-Put the synch. Check/manual selector switch to CHECK.
-Check permissive contact in synchronising check relay closes.
-Check the phase sequence at unit bus VT secondary terminals as detailed in following table. (It shall be same as that of associated station board).
MEASUREMENT IN VT CUBICLE
-Do the phasing out between VT secondaries of station and unit board.
-Keep the board charged for 24 Hours and observe it for any abnormality.