|
Check List
for 90% Model Review
|
1
|
The comments of
60% model review are closed.
|
2
|
Inter
discipline model review is conducted and comments of the same are
incorporated.
|
3
|
All Equipment
checked to IFC Vendor information.
|
4
|
All piping
modeled including piping below 2”
|
5
|
All Pipe
supports are modeled and checked
|
6
|
All Stress
comment incorporated and checked
|
7
|
All Steel
Structures are completed and checked with respect to IFC drawings
|
8
|
All Buildings
are completed and checked with respect to IFC drawings
|
9
|
All Foundations
are completed and checked with respect to IFC drawings
|
10
|
All Online,
Off-line and equipment mounted Instruments are completed and checked with
respect to approved vendor drawings.
|
11
|
All Telecom
items including CCTV’s, PAGA speakers are shown and checked
|
12
|
All Lighting
fixtures are completed and checked.
|
13
|
All electrical
panels / Distribution Boards are completed and checked.
|
14
|
All Fire &
Gas Equipment is completed and checked
|
15
|
All U/G
facilities completed and checked.
|
16
|
Any exclusion
from 60% model review is incorporated and checked.
|
17
|
All Utility
Stations are identified, located and checked for the maximum length of hose
with proper access.
|
18
|
All Safety
showers and eye baths are identified, located and checked with proper
access.
|
19
|
Location of
mobile and portable /manual firefighting equipment are shown and checked.
|
20
|
All Sample
connections are identified and modeled and checked for proper access.
|
21
|
The minor
access platforms, if any are located and checked for proper access.
|
22
|
The offline
instruments including analyzer enclosures/panels etc. are modeled at proper
locations and checked.
|
23
|
The fire and
gas detectors are shown and location of each is checked by HSE for function
and by piping for obstruction.
|
24
|
The cable
routing inside the building is complete and checked so that it is not
obstructing any movement of crane or walkways.
|
25
|
All the
instrument stands and supports are checked so that they are not obstructing
the walkways on the platforms especially in case of platforms located on
vertical vessels and columns.
|
|
26
|
Location of
junction boxes is checked so that they are not obstructing the walkways.
|
|
|
|
|
|
|
|
|
27
|
Junction
boxes/fire boxes are modeled with volume for door opening and does not
enter into the hard standing/access areas located for crane/walkways, etc.
|
|
|
|
|
|
|
|
|
28
|
Cable conduits
are checked so that they are not coming out in the middle of the road/
walkways.
|
|
|
|
|
|
|
|
|
29
|
Ensure that
arrangement of small bore piping has been done in such a way that the pipe
support is provided to prevent the breakage due to vibration.
|
|
|
|
|
|
|
|
|
30
|
Ensure purging
connection is provided at the dead end of flare header.
|
|
|
|
|
|
|
|
|
31
|
Ensure that
cooling water lines branch off from the header from top.
|
|
|
|
|
|
|
|
|
32
|
Ensure that
there are no valves installed with the stem pointing below the horizontal
plane in downward direction.
|
|
|
|
|
|
|
|
|
33
|
Ensure that the
vents from an analyzer house/cabinet are located and routed to atmosphere
at safe height from grade.
|
|
|
|
|
|
|
|
|
34
|
The vents of
seal chambers of reciprocating compressors are properly routed and
supported.
|
|
|
|
|
|
|
|
|
35
|
Unloading and
storage of chemicals and additives is reviewed for any environmental
impact.
|
|
|
|
|
|
|
|
|
36
|
Vendor trim
piping around equipment is put in the model and checked.
|
|
|
|
|
|
|
|
|
37
|
Ensure Toe
plate is modeled properly at platform opening.
|
|
|
|
|
|
|
|
|
38
|
Check that the
Siren/safety alarm system is installed at top of highest building and at
the centre of plant area.
|
|
|
|
|
|
|
|
|
39
|
The proper
lighting poles and fixtures etc. are shown and checked.
|
|
|
|
|
|
|
|
|
40
|
The safety
equipment like wind socks, breathing apparatus are strategically located as
per escape and safety equipment layout.
|
|
|
|
|
|
|
|
|
41
|
The routing of
branch cable trays to the instrument and support for the same is properly
shown and checked.
|
|
|
|
|
|
|
|
|
42
|
The parking
area, traffic barriers, boulders, etc. as applicable is modeled and
checked.
|
|
|
|
|
|
|
|
|
43
|
Steam tracing
manifolds and steam jacketing details are shown in model and checked.
|
|
|
|
|
|
|
|
|
44
|
All design
change notices (DCNs) are taken care with respect to completeness.
|
|
|
|
|
|
|
|
|