Review of other documents:

1) Utility summary:

This document shall reflect the various utilities consumed by each equipments with duty conditions like pressure, temperate, flow, state of fluid, critical data like freezing point etc.

2) Conceptual equipment layouts:

This document gives the general arrangement of the Equipments considering the process requirements like Inter-distances & approximate elevations of the equipments;

3) Piping material specification:

Basic material for piping items, valve specifications, special, flanges & gaskets required , any other specific requirement.

4) Type of storage required: This document shall mention the state of the fluid & type of equipment to be used for the storage like API Tank, silo, dehumidified atmosphere (warehouse), bullet horizontal / vertical) etc.

5) Hazard classification:

This documents gives the type of hazard for the fluids being handled ( like class a/b/c, flammability toxicity etc.) & the special precautions to be taken care.

6) Future expansion requirements:

These are to be mentioned by the client & to be taken care for the space requirement during the layout stage.