Pipeline Fabrication

Pipeline Fabrication and Installation Activities includes pipe bending, welding, pipeline string, pipeline lowering etc.

Pipeline Dump Sites

Acquiring of land and development of dump site

1.    Grading of land.

2.    Providing temporary fencing, barrier gate, guard room and security.

3.    Providing internal roads (WBM) for trailer movement and area lighting with DG Set.

4.    Providing sand rows for stacking of coated pipes.

 Handling of Coated Pipes

1.    Adequate cranes with padded hooks for unloading / loading of coated pipes in trailers.

2.    Stacking of coated pipes on sand rows.

3.    Holiday check and visual check including gauge plate pull test before despatch to site.