Step by Step Dye Penetrant Testing
The article addresses a step by step dye penetrant testing process. There are two techniques for dye penetrant test as follow:
Each of above techniques can be performed with three different processes as follow:
In this article, we are going to explain the simplest technique and process which is used for portable application in the field. Some of the above-mentioned processes are designed for lab test application and would not be easy to be conducted in the field. Here is the step by step dye penetrant testing process:
Step 1 - Precleaning of the Surface
The 3 spray cans (aerosol) are provided for this test. First one is named cleaner. The technician sprays the cleaner to the test object and then cleans the surface with non-used rag or cloth. The sprayed material is evaporated rapidly. So the technsion needs to clean the surface instantly.
Step 2- Application of Penetrant
In the second step, the technician applies penetrant spray can to the surface which is in sharp red color. The technician needs to wait for 5 to 15 minutes depends on test procedure. In this time, the penetrant liquid enters to the crack (normally is not visible). The penetrant liquid soaks inside of the defects/ imperfections by capillary action.
Step 3- Removal of the Excess Penetrant Liquid
In the third step, the technician removes penetrant liquid from the surface by rag or cloth and uses back and forth rubbing to clean the surface. No red color should be visible after cleaning. Then technison takes a clean rag and sprays some cleaner on a cloth and then cleans the surface one more time. This can be done two or three times to remove all penetrant liquid from the surface. Please note by the capillary action; the penetrant liquid still is in the cracks or hot tear or any other imperfection. It will not come out by cleaning as described.
Step 4 - Application of Developer
In the fourth step, the technician takes the developer spray can and agitates it and then sprays to the surface. Then he waits for 10 minutes. In this time, the defect will be visible, the developer material uses reverse capillary action and bleeds out the red penetrant, and if there is a crack in the surface, you will see a red line within the white color covered by developer material.
Step 5 - Evaluation / Interpretation
In the fifth step, The ASNT Level II liquid penetrant inspector evaluates the test result based on the acceptance criteria indicated in the approved test procedure. Please note one indication might be considered imperfection and be rejected by one acceptance criteria and be accepted by another one. So it is imperative that the test be evaluated with right acceptance criteria.
Step 6 - Liquid Penetrant Test Report
In the sixth step, The technician prepares the report and indicates the test results and submits to the customer.